We are committed to delivering excellence in client service. However, the
home-building process involves many moving parts, including the challenge of
scheduling tradespeople for work in your new home after possession. Following the
Pre-Delivery Inspection (PDI), which takes place 5 to 10 days before possession, we
will make every effort to complete all items on the list prior to your occupancy.
Afterward, we provide a 30-day form, included in your PDI package , allowing you
to add any additional items you may notice while living in the home. In both cases,
Tarion guidelines state that the builder
has 120 days to complete the items on either list. The final opportunity for
additional repairs is known as the Year-End List, which can be submitted 12
months after possession.